PEI Energy Corporation says the second phase of some repairs to the Hermanville Wind Farm is underway. Because of turbine issues, the Hermanville Wind Farm has not been operating at its peak ability due to turbine issues. In 2023, there were major repairs to 5 of the turbines, and those repairs have resulted in better energy generation. In fact, April 2024 was the best energy producing month in more than two years at over 6,000 megawatt hours produced from eight turbines, with four of those turbines running above 97% availability. Phase two of the repairs is underway, as a crane is on-site to help with repairs to three turbines. Phase two repairs are expected to be complete by the end of August.